Bio mass boiler installation
Installation of mains supplies and SELV control wiring
Installation of mains supplies and SELV control wiring
This job consisted of installing new sub mains into the plant room to supply both the new biomass boiler and also a back up immersion heater.
We also had to install all the control wiring for sensors, stats and thermal cut outs. Because there was a mixture of both mains voltage and SELV in close proximity the manufactures specified that all cable should be CY flex which is a screened and shielded cable.
This was a complete new installation consisting of cubical housing, AMS area, plant room and dairy.
This was a relativly small electrical installation consisting of four 50w LED floods inside the shed and one 30w flood outside controlled off a photocell. The client was extremely happy with the LED light and we have since installed more on the farm